The concrete slab at the employee entrance at Lutheran Hospital is exposed to all types of weather through the year. Exposure to deicing materials caused the concrete to deteriorate, requiring repair. The schedule for completion of the work was difficult since the entrance could only be closed for two days.
Western Specialty Contractors’ Des Moines office was selected to complete the repair. A new flexible epoxy was utilized for the work. The material has a rapid cure time, both for patching and coating. This was essential for this project.
The work was completed in two days and the entrance is ready to safely serve the hospital employees again.